Capital Improvements Projects (CIP) are designated improvements to the Lincoln City Golf Courses identified within the CIP 10 Year Plan (updated 2023). Important updates to our courses include but are not limited to the repair of cart paths and tee boxes, replacement of irrigation and other mechanical structures, and improving the greens and landscaping to gradually improve our public courses.
Where do the funds for CIP projects come from?
Surcharge fees are the added charges that are included in the price of golf at a Lincoln City Golf Course. (A total of $2.50 to the price of 18 holes and $1.25 to the price of 9 holes.)
The Capital Improvement Projects (CIP) charge adds $1.50 will be added to all 18 hole green fees and $.75 to all 9 hole green fees.
Pioneers Irrigation Surcharge Fee: $.50 will be added to all 9 hole green fees at the four 18 hole golf courses. $1.00 will be added to all 18 hole green fees at the four 18 hole golf courses. This fee contributes to the payment of the 10-year bond for the new Pioneers Irrigation system.
Links
- CIP 10 Year Plan (Final Plan – Updated 2023) (PDF download)
Current Projects
2026 Pioneers Golf Cart Path Replacement Project, $413,603
- Complete replacement of cart paths on the course
- Project was completed in April of 2026
2025 Holmes Park Golf Irrigation Project, $1.998 million
- Started September 2025
- Wrapped up in Spring of 2026
- The current irrigation system is 40 years old and past its useful life as typical irrigation systems last about 25-30 years.
Future Projects
General
- Cart Path replacements at Holmes and Highlands
- Tree replanting
- Bunker restorations
- Drinking fountain replacement
Highlands
- Renovate restrooms on course
- Remove seawall and add rip-rap to pond
- Cold storage building
Holmes
- New practice area with putting green and bunkers
- Rebuild existing putting green
- Cold storage building
Jim Ager
- New maintenance shop with HVAC units
- Replacement of driving range netting/concrete footings
- Parking lot replacement
- Renovate clubhouse building
Mahoney
- Replace irrigation pump station
- Parking lot replacement
- New siding/windows/ roof shingles
- Pond wall restoration
- Driving range netting
- Replace irrigation system
Pioneers
- Replace concrete floor in east maintenance shop
- Complete Clubhouse renovation
- Re-seeding of roughs
Previous Projects
Hover mouse over below images to view progress of construction.









2024 continued
Mahoney
- Replacement of carpet in clubhouse $6,903
- Replacement of gutters/downspouts $4,912
- New clubhouse lawn irrigation $16,070
- Sod for forward tee boxes $10,978
- Driving range net repairs/replacement $14,800
Holmes
- Parking lot sealing $5,066
- Clubhouse concrete repairs $36,027
- Engineering services design irrigation system $27,164
- Sod for forward tee boxes $8,084
Highlands
- Clubhouse concrete patio replacement $5,850
- Parking lot sealing $3,050
- Cart path replacement $27,468
Jim Ager
- Tree removal $7,084
- Fencing near #1 green $8,471
Pioneers
- Cart path replacement $28,642
- Parking lot sealing $4,746
- Replacement of Irrigation pond in-fill line $72,499
- Tree removals $45,610
- Sod forward tee boxes $11,903
- New fencing near entrance $17,381

Photo Gallery
- Highlands Parking Lot Replacement
- Highlands pump panel 2020
- Shelter at Highlands after roof repair 2021
- Highlands clubhouse 2021
- Highlands restroom renovation 2021
- Holmes cart path 2017
- Holmes cart path 2017 after
- Holmes cart path 2017 before
- Ash Tree Removal at Holmes 2019
- Pioneers clubhouse roof 2020
- Pioneers clubhouse roofing 2020
- Pioneers pumphouse 2017
- Pioneers Pump Station 2018